![](https://www.rexbishopandson.co.uk/wp-content/uploads/2021/12/Temporary-weather-proofing-structural-steel-installed-to-Gym-building.jpg)
![](https://www.rexbishopandson.co.uk/wp-content/uploads/2021/12/Music-building.jpg)
![](https://www.rexbishopandson.co.uk/wp-content/uploads/2021/12/Music-building-demolition.jpg)
![](https://www.rexbishopandson.co.uk/wp-content/uploads/2021/12/Music-building-completed.jpg)
![](https://www.rexbishopandson.co.uk/wp-content/uploads/2021/12/Gym-roof-removal-by-hand.jpg)
![](https://www.rexbishopandson.co.uk/wp-content/uploads/2021/12/Gym-roof-removal-by-hand-completed.jpg)
![](https://www.rexbishopandson.co.uk/wp-content/uploads/2021/12/Gym-roof-removal-by-hand-b.jpg)
![](https://www.rexbishopandson.co.uk/wp-content/uploads/2021/12/Gym-building-being-demolished-by-hand.jpg)
![](https://www.rexbishopandson.co.uk/wp-content/uploads/2021/12/Gym-Building-completed.jpg)
![](https://www.rexbishopandson.co.uk/wp-content/uploads/2021/12/Designed-scaffolding-to-Gym-building-building.jpg)
![](https://www.rexbishopandson.co.uk/wp-content/uploads/2021/12/concrete-floor-slab-removal.jpg)
Asbestos
Don't hide it, remove it!
Client: Gardiner & Theobald LLP on behalf of westonbirt school
Project Overview:
Client: Gardiner & Theobald LLP on behalf of westonbirt school
Location: westonbirt School Tetbury Gloucestershire
Project Manager: Neil Bishop
Site Manager: Jake Simpson
Duration: 12 weeks
Project Overview: The F10 notified project was to carry asbestos removal & disposal. Demolish the music & Gym building in very tight restraints.
Scope of Works:
Demolition & site clearance
Asbestos Removal.
Designed scaffolding around Gym building.